SAT Math Practice Question
The formula below is often used by project managers to compute $E$, the estimated time to complete a job, where $O$ is the shortest completion time, $P$ is the longest completion time, and $M$ is the most likely completion time.$$E=\frac{O+4 M+P}{6}$$Which of the following correctly gives $P$ in terms of $E, O$, and $M$ ?
- A.$P=6 E-O-4 M$
- B.$P=-6 E+O+4 M$
- C.$P=\frac{O+4 M+E}{6}$
- D.$P=\frac{O+4 M-E}{6}$
Want to know if you got it right?
Answer this and thousands more real SAT previous-year questions free, get graded instantly, and climb the global ranked leaderboard.
Practice SAT free →More SAT Math questions
- If \frac{x-1}{3}=k and k=3, what is the value of x ?…
- For i=\sqrt{-1}, what is the sum (7+3 i)+(-8+9 i) ?…
- On Saturday afternoon, Armand sent m text messages each hour for 5 hours, and Tyrone sent …
- Kathy is a repair technician for a phone company. Each week, she receives a batch of phone…
- \left(x^{2} y-3 y^{2}+5 x y^{2}\right)-\left(-x^{2} y+3 x y^{2}-3 y^{2}\right)Which of the…
- h=3 a+28.6A pediatrician uses the model above to estimate the height h of a boy, in inches…
- m=\frac{\left(\frac{r}{1,200}\right)\left(1+\frac{r}{1,200}\right)^{N}}{\left(1+\frac{r}{1…
- If \frac{a}{b}=2, what is the value of \frac{4 b}{a} ?…