JEE Math Practice Question

A software company sets up m number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of $$\mathrm{m}$$ is equal to:

  1. A.125
  2. B.160
  3. C.150
  4. D.180